"2022 SP 074"
2 agenda items mention this keyword
Authorize a cost adjustment, no budgetary impact - Tender 2022 SP 074 - Reconstruction of boulevard de la Gappe and rue Sillery - Touraine electoral district - Tiffany-Lee Norris-Parent
This item seeks approval for a cost adjustment related to the reconstruction of boulevard de la Gappe and rue Sillery. The adjustment is budget-neutral, meaning it does not require additional funding beyond what was previously allocated.
infrastructure
Authorize a cost adjustment, budget-neutral - Tender 2022 SP 074 - Reconstruction of boulevard de la Gappe and rue de Sillery
The Executive Committee approved an additional $82,902.72 in professional fees for the engineering firm CITEK s.e.n.c. regarding the reconstruction project for boulevard de la Gappe and rue de Sillery. This adjustment, along with previously approved minor modifications, brings the total cumulative adjustment to $91,773.14. The city confirms this increase is budget-neutral.
infrastructurebudget