"Saint-Gérard"
4 agenda items mention this keyword
Authorize a cost adjustment, with no budgetary impact - Tender 2023 SP 190 - Reconstruction of the Saint-Gérard Community Centre
This item seeks approval for a cost adjustment related to the reconstruction of the Saint-Gérard Community Centre. The adjustment is budget-neutral, meaning it does not require additional funding from the city.
infrastructurebudget
Authorize a cost adjustment, budget-neutral - Tender 2023 SP 190 - Reconstruction of the Saint-Gérard Community Centre
The committee approved a cost increase of $252,805.11 for the reconstruction of the Saint-Gérard Community Centre due to additional change orders. This adjustment is budget-neutral, meaning it does not require new funding, and brings the total contract value to $6,454,308.09.
infrastructurebudget
Tender 2023 SP 190 - Reconstruction of the Saint-Gérard community centre - Project 21-2078 - Infrastructure and Projects Department - Rivière-Blanche electoral district - Jean Lessard
This item addresses the reconstruction of the Saint-Gérard community centre. The project, managed by the Infrastructure and Projects Department, aims to replace the aging facility with a new building to better serve the local community. This is a significant capital investment for the Rivière-Blanche district.
infrastructureculture
Integration of public art into the future Saint-Gérard community centre - Rivière-Blanche electoral district - Jean Lessard
This item approves the integration of a public art piece into the new Saint-Gérard community centre, located in the Rivière-Blanche district represented by Councillor Jean Lessard.
culture