Authorize a cost adjustment for work, with budgetary impact - Tender 2021 SP 315 - Partial repair of the discharge pipe at the Angers pumping station - Masson-Angers electoral district - Mario Dubé
This item requests approval for a budget increase for the partial repair of the Angers pumping station discharge pipe. The adjustment is necessary to cover additional costs associated with the project.
infrastructurebudget
Cost Adjustment for Partial Refurbishment of the Angers Pumping Station Discharge Pipe
The Executive Committee approved a cost increase of $240,777.66 for the partial refurbishment of the Angers pumping station discharge pipe. This adjustment covers 10 new change orders required to finalize the project, bringing the total contract value to $2,564,312.21. This expenditure has a budgetary impact.