Major decisions
9 #
Demolition of a single-family home – 487, chemin McConnell – Deschênes electoral district – Caroline Murray
The committee approved the demolition of a vacant single-family home built in 1960 at 487, chemin McConnell. The site is slated for a new 15-storey residential building containing 503 units, pending further council approvals for zoning and conditional use.
Read full translation

R-CDD-2024-10-08/55

CONSIDERING THAT a request to demolish a vacant, one-storey, detached single-family residential building has been submitted for the property located at 487, chemin McConnell;

CONSIDERING THAT the existing main building, constructed in 1960, has no recognized heritage value and is not identified in the document Ville de Gatineau - Inventaire du patrimoine bâti - 2008;

CONSIDERING THAT there are no active complaint files regarding the deterioration of neighborhood quality of life concerning the building to be demolished;

CONSIDERING THAT the construction project constituting the proposed reuse program for the cleared land aims for the construction of a new 15-storey residential building containing 503 housing units;

CONSIDERING THAT the construction project constituting the proposed reuse program for the cleared land is evolving and could be subject, if required, to council approval of minor derogation(s) to Règlement de zonage numéro 532-2020;

CONSIDERING THAT the construction project constituting the proposed reuse program for the cleared land must be approved by the council, pursuant to Règlement relatif aux usages conditionnels numéro 506-2005, as the project will contain more than 100 housing units;

CONSIDERING THAT the Demolition Review Committee (CDD) may set the conditions necessary for the issuance of a demolition certificate;

CONSIDERING THAT before rendering its decision, the Committee took into account all evaluation criteria listed in Article 22 of règlement numéro 900-2021;

CONSIDERING THAT no opposition was received following the publication of the public notice of demolition on September 25, 2024;

CONSIDERING THAT this Committee is convinced of the appropriateness of the complete demolition of the building, given the public interest and the interest of the parties;

AND RESOLVED THAT this Committee approves, pursuant to Règlement visant à régir la démolition d'immeubles sur le territoire de la Ville de Gatineau numéro 900-2021, the demolition of the single-family home located at 487, chemin McConnell, conditionally upon:

  1. Authorization of the preliminary reuse program for the cleared land by the council pursuant to Règlement relatif aux usages conditionnels numéro 506-2005;
  2. The granting, if required, by the municipal council of minor derogation(s) to Règlement de zonage numéro 532-2020;
  3. The simultaneous issuance of the building permit for the replacement project approved by the municipal council and the authorization certificate for the demolition work.

ADOPTED UNANIMOUSLY

zoninghousing adopted Deschênes 487, chemin McConnell 900-2021532-2020506-2005 487 chemin McConnelldemolitionresidential developmentRèglement 900-2021
Notable items
10 #
Demolition of a single-family home – 17, rue Davies – Manoir-des-Trembles-Val-Tétreau electoral district – Jocelyn Blondin
The committee approved the demolition of a single-family home at 17, rue Davies. This project is part of a combined development with 19, rue Davies to build a four-storey, 11-unit residential building. The approval is conditional on council granting minor zoning derogations.
Read full translation

R-CDD-2024-10-08/56

CONSIDERING THAT a request to demolish an occupied single-family home has been submitted for the property located at 17, rue Davies;

CONSIDERING THAT the existing main building, constructed in 1958, has no recognized heritage value and is not identified in the document Ville de Gatineau – Inventaire du patrimoine bâti – 2008;

CONSIDERING THAT according to the applicant, the building is in good condition and does not require restoration work;

CONSIDERING THAT a complaint file is active regarding the deterioration of neighborhood quality of life concerning the building to be demolished;

CONSIDERING THAT the preliminary reuse program for the cleared land consists of consolidating the lots at 17, rue Davies and 19, rue Davies, in order to build a four-storey residential building containing 11 housing units;

CONSIDERING THAT the construction project constituting the preliminary reuse program for the cleared land must be subject to council approval for minor derogations to Règlement de zonage numéro 532-2020, notably for front and side street setbacks;

CONSIDERING THAT the Demolition Review Committee (CDD) may set the conditions necessary for the issuance of a demolition certificate;

CONSIDERING THAT before rendering its decision, the Committee took into account all evaluation criteria listed in Article 22 of règlement numéro 900-2021;

CONSIDERING THAT before rendering its decision, the Committee took into account the oppositions received following the publication of the public notice of demolition on September 25, 2024;

CONSIDERING THAT this Committee is convinced of the appropriateness of the complete demolition of the building, given the public interest and the interest of the parties;

AND RESOLVED THAT this Committee approves, pursuant to Règlement visant à régir la démolition d'immeubles sur le territoire de la Ville de Gatineau numéro 900-2021, the demolition of the residential building located at 17, rue Davies, conditionally upon:

  1. The granting, by the council, of minor derogations to Règlement de zonage numéro 532-2020 for the implementation of the preliminary reuse program for the cleared land;
  2. The simultaneous issuance of the building permit for the replacement project and the authorization certificate for the demolition work.

ADOPTED UNANIMOUSLY

zoninghousing adopted Manoir-des-Trembles-Val-Tétreau 17, rue Davies 900-2021532-2020 17 rue Daviesdemolitionresidential developmentRèglement 900-2021
11 #
Demolition of a single-family home – 1441, boulevard Saint-René Est – Rivière-Blanche electoral district – Jean Lessard
The committee approved the demolition of a single-family home at 1441, boulevard Saint-René Est. The site is planned for a new six-storey residential building with 84 units. The approval is conditional on council granting any necessary minor zoning derogations.
Read full translation

R-CDD-2024-10-08/58

CONSIDERING THAT a request to demolish a detached single-family home has been submitted for the property located at 1441, boulevard Saint-René Est;

CONSIDERING THAT the existing main building, constructed in 1975, has no recognized heritage value and is not identified in the document Ville de Gatineau – Inventaire du patrimoine bâti – 2008;

CONSIDERING THAT according to the inspection report carried out by the firm Inspections Baizana Inc. on February 2, 2024, work would eventually be required, such as repairs to foundation cracks, plumbing, electricity, and the heating system, in order to bring the building into compliance with current construction standards;

CONSIDERING THAT according to this same inspection report, the recommended work is estimated between $100,000 and $150,000;

CONSIDERING THAT there are no active complaint files regarding the deterioration of neighborhood quality of life concerning the building to be demolished;

CONSIDERING THAT the building is currently occupied, but the tenant has signed an open-ended lease and has been informed of the owner's intentions regarding the demolition of the building;

CONSIDERING THAT the preliminary reuse program for the cleared land consists of building a six-storey residential building containing 84 housing units;

CONSIDERING THAT the construction project constituting the preliminary reuse program for the cleared land is evolving and could be subject to council approval of minor derogation(s) to Règlement de zonage numéro 532-2020;

CONSIDERING THAT the Demolition Review Committee (CDD) may set the conditions necessary for the issuance of a demolition certificate;

CONSIDERING THAT before rendering its decision, the Committee took into account all evaluation criteria listed in Article 22 of règlement numéro 900-2021;

CONSIDERING THAT no opposition was received following the publication of the public notice of demolition on September 25, 2024;

CONSIDERING THAT this Committee is convinced of the appropriateness of the complete demolition of the building, given the public interest and the interest of the parties;

AND RESOLVED THAT this Committee approves, pursuant to Règlement visant à régir la démolition d'immeubles sur le territoire de la Ville de Gatineau numéro 900-2021, the demolition of a detached single-family home located at 1441, boulevard Saint-René Est, conditionally upon:

  1. The granting, if required, by the council, of minor derogations to Règlement de zonage numéro 532-2020 for the implementation of the preliminary reuse program for the cleared land;
  2. The simultaneous issuance of the building permit for the replacement project and the authorization certificate for the demolition work.

ADOPTED UNANIMOUSLY