Authorization of a Cost Adjustment for Professional Consulting Engineering Fees, No Budgetary Impact - 2019 SP 078 - Les Services EXP inc. - Buckingham Electoral District - Edmond Leclerc
The City is approving additional professional fees of $155,617.51 for Les Services EXP inc. regarding the Smith Creek retention basin project. These costs cover additional surveying, stability studies, and redesign work, bringing the total project cost to $520,347.13. This adjustment has no net impact on the city budget.
infrastructurebudget
Authorization of a Cost Adjustment, No Budgetary Impact - Submission 2025 SP 016 - 2025 Qualitative Material Control - Infrastructure and Projects Department
The City is authorizing additional professional laboratory fees for material quality control due to new projects added to the 2025 schedule. This includes $496,198.96 for Lot 1 (Buckingham, Gatineau, Masson-Angers) and $355,222.18 for Lot 2 (Aylmer, Hull). These adjustments have no net impact on the city budget.
infrastructurebudget
Authorization of a Cost Adjustment for Professional Consulting Engineering Fees, No Budgetary Impact - Submission 2022 SP 058 - Road Reconstruction of Boulevard Lucerne, between Chemin Vanier and Avenue Frank-Robinson - Infrastructure and Projects Department - Deschênes and Aylmer Electoral Districts - Caroline Murray and Steven Boivin
The City is approving additional professional fees of $187,662.20 for Les Services EXP inc. for the Boulevard Lucerne reconstruction project. These costs cover geometric modifications, the addition of rapid-flashing beacons, and geotechnical rock characterization. The total revised mandate cost is $899,504.54, with no net impact on the city budget.
infrastructurebudget
Project 141968 - Authorize a cost adjustment for consulting engineering fees, without budgetary impact - Les Services EXP inc. - Saint-Joseph storm sewer construction project, between Alexandre-Taché Boulevard and the Ottawa River
This item approves a change in professional fees for the Saint-Joseph storm sewer project. The adjustment is budget-neutral, meaning it does not require additional city funds.
infrastructurebudget
Authorize a cost adjustment for professional engineering fees, without budgetary impact, for the Saint-Joseph storm sewer construction project
The city is approving an additional $173,044.73 in professional fees for *Les Services EXP inc.* regarding the Saint-Joseph storm sewer project. This adjustment covers design and plan modifications and does not require additional budget as it is offset by previous adjustments.
infrastructurebudget
Authorization of a Cost Adjustment for Professional Consulting Engineering Fees, Budget Neutral - Les Services EXP inc. - Extension of Municipal Services on Rue de Vernon - Phases 1 and 2
The City approved an additional $47,369.03 for Les Services EXP inc. for engineering work related to the extension of municipal services on Rue de Vernon. This includes updates to environmental assessments and groundwater characterization.