Authorize a cost adjustment for work, no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, rue Principale, Aylmer sector
The city is approving additional costs for the construction of the Lucy-Faris Library due to change orders. These extra costs, totaling $296,336.22 (including taxes), are being covered without requiring new budget allocations. The total adjusted contract value for the project is now $43,504,949.20.
infrastructurebudget
Authorize a cost adjustment for work, no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, Rue Principale
The committee approved additional costs of $395,988.34 for the construction of the Lucy-Faris Library. These costs, related to various change orders, do not require additional budget as they are covered within existing project allocations. The total adjusted contract value is now $43,208,612.98.
infrastructurebudget
Authorization of a Cost Adjustment for Construction Work, No Budgetary Impact - Submission 2022 SP 339 - Lucy-Faris Library - 115, Rue Principale, Aylmer Sector
The City is approving an additional $531,284.80 for construction costs at the Lucy-Faris Library project in Aylmer. This covers change orders and additional work, bringing the total contract value to $42,812,624.64, with no impact on the city budget.