Demolition of a single-family residential building – 168 Eardley Road – Aylmer District – Steven Boivin
The committee approved the demolition of a vacant single-family home at 168 Eardley Road. This is part of a larger, four-phase mixed-use development project that will eventually include a six-story building with 142 housing units. The demolition is conditional upon the final approval of the new construction plans, compliance with zoning and architectural bylaws, and the simultaneous issuance of demolition and construction permits.
Read full translation

CONSIDERING THAT a request to demolish a vacant single-family residential main building has been submitted for the property located at 168 Eardley Road;

CONSIDERING THAT the existing main building, constructed in 1947, has no recognized heritage value and is not identified in the document Ville de Gatineau — Inventaire du patrimoine bâti — 2008;

CONSIDERING THAT the applicant states the building is in poor condition and requires restoration work estimated at approximately $221,850;

CONSIDERING THAT the preliminary reuse program for the cleared land aims for the construction of a six-story residential building containing 142 housing units, all part of an integrated mixed-use project divided into four phases;

CONSIDERING THAT no complaints regarding the deterioration of neighborhood quality of life related to the building to be demolished are active, but the building is currently boarded up;

CONSIDERING THAT the construction project constituting the preliminary reuse program for the cleared land must be approved by the council under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005, and that its evolving design may lead to the need for the council to grant minor variances to the Règlement de zonage numéro 532-2020;

CONSIDERING THAT the construction project for the phase 1 building must be approved by the council under the Règlement relatif aux usages conditionnels numéro 506-2005, as the project will include more than 100 housing units;

CONSIDERING THAT the Demolition Committee may set the conditions necessary for the issuance of a demolition certificate;

CONSIDERING THAT before rendering its decision, the Committee took into account all evaluation criteria listed in Article 22 of Règlement numéro 900-2021;

CONSIDERING THAT no opposition was received following the publication of the public notice of demolition on May 1, 2024;

CONSIDERING THAT this Committee is convinced of the appropriateness of the complete demolition of the building, given the public interest and the interest of the parties;

AND RESOLVED THAT this Committee approves, under the Règlement visant à régir la démolition d’immeubles sur le territoire de la Ville de Gatineau numéro 900-2021, the demolition of the residential building located at 168 Eardley Road, conditional upon:

• The approval of the construction project constituting the reuse program for the cleared land under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005; • The granting, by the council, of a conditional use for any building intended to be occupied by 100 or more housing units under the Règlement relatif aux usages conditionnels numéro 506-2005; • The granting, by the council, of minor variances to the Règlement de zonage numéro 532-2020, if required; • The simultaneous issuance of the building permit for the replacement project and the certificate of authorization for the demolition work.

UNANIMOUSLY ADOPTED

zoninghousing adopted Aylmer 168, chemin Eardley 900-2021505-2005532-2020506-2005 168 Eardley RoaddemolitionAylmerredevelopment $221,850
5 #
Demolition of a single-family residential building – 172 Eardley Road – Aylmer District – Steven Boivin
The committee approved the demolition of a vacant single-family home at 172 Eardley Road. This is part of a larger, four-phase mixed-use development project that will eventually include a six-story building with 142 housing units. The demolition is conditional upon the final approval of the new construction plans, compliance with zoning and architectural bylaws, and the simultaneous issuance of demolition and construction permits.
Read full translation

CONSIDERING THAT a request to demolish a vacant single-family residential main building has been submitted for the property located at 172 Eardley Road;

CONSIDERING THAT the existing main building, constructed in 1943, has no recognized heritage value and is not identified in the document Ville de Gatineau — Inventaire du patrimoine bâti — 2008;

CONSIDERING THAT the applicant states the building is in poor condition and requires restoration work estimated at approximately $143,550;

CONSIDERING THAT the preliminary reuse program for the cleared land aims for the construction of a six-story residential building containing 142 housing units, all part of an integrated mixed-use project divided into four phases;

CONSIDERING THAT no complaints regarding the deterioration of neighborhood quality of life related to the building to be demolished are active, but the building is currently boarded up;

CONSIDERING THAT the construction project constituting the preliminary reuse program for the cleared land must be approved by the council under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005, and that its evolving design may lead to the need for the council to grant minor variances to the Règlement de zonage numéro 532-2020;

CONSIDERING THAT the construction project for the phase 1 building must be approved by the council under the Règlement relatif aux usages conditionnels numéro 506-2005, as the project will include more than 100 housing units;

CONSIDERING THAT before rendering its decision, the Committee took into account all evaluation criteria listed in Article 22 of Règlement numéro 900-2021;

CONSIDERING THAT no opposition was received following the publication of the public notice of demolition on May 1, 2024;

CONSIDERING THAT this Committee is convinced of the appropriateness of the complete demolition of the building, given the public interest and the interest of the parties;

AND RESOLVED THAT this Committee approves, under the Règlement visant à régir la démolition d’immeubles sur le territoire de la Ville de Gatineau, numéro 900-2021, the demolition of the residential building located at 172 Eardley Road, conditional upon:

• The approval of the construction project constituting the reuse program for the cleared land under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005; • The granting, by the council, of a conditional use for any building intended to be occupied by 100 or more housing units under the Règlement relatif aux usages conditionnels numéro 506-2005; • The granting, by the council, of minor variances to the Règlement de zonage numéro 532-2020, if required; • The simultaneous issuance of the building permit for the replacement project and the certificate of authorization for the demolition work.

UNANIMOUSLY ADOPTED

zoninghousing adopted Aylmer 172, chemin Eardley 900-2021505-2005532-2020506-2005 172 Eardley RoaddemolitionAylmerredevelopment $143,550
5 #
Demolition of a residential building – 176 Eardley Road – Aylmer District – Steven Boivin
The committee approved the demolition of a vacant single-family home at 176 Eardley Road. This is part of a larger, four-phase mixed-use development project that will eventually include a six-story building with 142 housing units. The demolition is conditional upon the final approval of the new construction plans, compliance with zoning and architectural bylaws, and the simultaneous issuance of demolition and construction permits.
Read full translation

CONSIDERING THAT a request to demolish a vacant single-family residential main building has been submitted for the property located at 176 Eardley Road;

CONSIDERING THAT the existing main building, constructed in 1973, has no recognized heritage value and is not identified in the document Ville de Gatineau — Inventaire du patrimoine bâti — 2008;

CONSIDERING THAT the applicant states the building is in poor condition and requires restoration work estimated at approximately $230,550;

CONSIDERING THAT the preliminary reuse program for the cleared land aims for the construction of a six-story residential building containing 142 housing units, all part of an integrated mixed-use project divided into four phases;

CONSIDERING THAT no complaints regarding the deterioration of neighborhood quality of life related to the building to be demolished are active, but the building is currently boarded up;

CONSIDERING THAT the construction project constituting the preliminary reuse program for the cleared land must be approved by the council under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005, and that its evolving design may lead to the need for the council to grant minor variances to the Règlement de zonage numéro 532-2020;

CONSIDERING THAT the construction project for the phase 1 building must be approved by the council under the Règlement relatif aux usages conditionnels numéro 506-2005, as the project will include more than 100 housing units;

CONSIDERING THAT before rendering its decision, the Committee took into account all evaluation criteria listed in Article 22 of Règlement numéro 900-2021;

CONSIDERING THAT no opposition was received following the publication of the public notice of demolition on May 1, 2024;

CONSIDERING THAT this Committee is convinced of the appropriateness of the complete demolition of the building, given the public interest and the interest of the parties;

AND RESOLVED THAT this Committee approves, under the Règlement visant à régir la démolition d’immeubles sur le territoire de la Ville de Gatineau, numéro 900-2021, the demolition of the residential building located at 176 Eardley Road, conditional upon:

• The approval of the construction project constituting the reuse program for the cleared land under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005; • The granting, by the council, of a conditional use for any building intended to be occupied by 100 or more housing units under the Règlement relatif aux usages conditionnels numéro 506-2005; • The granting, by the council, of minor variances to the Règlement de zonage numéro 532-2020, if required; • The simultaneous issuance of the building permit for the replacement project and the certificate of authorization for the demolition work.

UNANIMOUSLY ADOPTED

zoninghousing adopted Aylmer 176, chemin Eardley 900-2021505-2005532-2020506-2005 176 Eardley RoaddemolitionAylmerredevelopment $230,550
5 #
Demolition of a single-family residential building – 21 Riley Alley – Aylmer District – Steven Boivin
The committee approved the demolition of a vacant single-family home at 21 Riley Alley. This is part of a larger, four-phase mixed-use development project that will eventually include a six-story building with 142 housing units. The demolition is conditional upon the final approval of the new construction plans, compliance with zoning and architectural bylaws, and the simultaneous issuance of demolition and construction permits.
Read full translation

CONSIDERING THAT a request to demolish a vacant single-family residential main building has been submitted for the property located at 21 Riley Alley;

CONSIDERING THAT the existing main building, constructed in 1973, has no recognized heritage value and is not identified in the document Ville de Gatineau — Inventaire du patrimoine bâti — 2008;

CONSIDERING THAT the applicant states the building is in poor condition and requires restoration work estimated at approximately $134,850;

CONSIDERING THAT the preliminary reuse program for the cleared land aims for the construction of a six-story residential building containing 142 housing units, all part of an integrated mixed-use project divided into four phases;

CONSIDERING THAT no complaints regarding the deterioration of neighborhood quality of life related to the building to be demolished are active, but the building is currently boarded up;

CONSIDERING THAT the construction project constituting the preliminary reuse program for the cleared land must be approved by the council under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005, and that its evolving design may lead to the need for the council to grant minor variances to the Règlement de zonage numéro 532-2020;

CONSIDERING THAT the construction project for the phase 1 building must be approved by the council under the Règlement relatif aux usages conditionnels numéro 506-2005, as the project will include more than 100 housing units;

CONSIDERING THAT before rendering its decision, the Committee took into account all evaluation criteria listed in Article 22 of Règlement numéro 900-2021;

CONSIDERING THAT no opposition was received following the publication of the public notice of demolition on May 1, 2024;

CONSIDERING THAT this Committee is convinced of the appropriateness of the complete demolition of the building, given the public interest and the interest of the parties;

AND RESOLVED THAT this Committee approves, under the Règlement visant à régir la démolition d’immeubles sur le territoire de la Ville de Gatineau numéro 900-2021, the demolition of the residential building located at 21 Riley Alley, conditional upon:

• The approval of the construction project constituting the reuse program for the cleared land under the Règlement relatif aux plans d’implantation et d’intégration architecturale numéro 505-2005; • The granting, by the council, of a conditional use for any building intended to be occupied by 100 or more housing units under the Règlement relatif aux usages conditionnels numéro 506-2005; • The granting, by the council, of minor variances to the Règlement de zonage numéro 532-2020, if required; • The simultaneous issuance of the building permit for the replacement project and the certificate of authorization for the demolition work.

UNANIMOUSLY ADOPTED

zoninghousing adopted Aylmer 21, allée Riley 900-2021505-2005532-2020506-2005 21 Riley AlleydemolitionAylmerredevelopment $134,850