Notable items
CM-2024-251 #
St-Gérard Community Centre - Additional Funding - Use of Contingency Fund
The City Council approved an additional $3,599,865 from the contingency fund to cover the increased construction costs of the St-Gérard Community Centre. The project budget rose to $6.5 million due to updated estimates and the uncertainty surrounding a $750,000 federal grant. If the grant is eventually received, the funds will be returned to the contingency reserve.
Read full translation

CONSIDERING THAT in May 2022, resolution number CM-2022-341 authorized the treasurer to draw an amount of $1,578,000 from the City's free surplus (the contingency fund), representing the difference between the reconstruction costs of the Centre communautaire Saint-Gérard ($3,650,135) and the sums already received from the insurance company ($1,322,135) as well as the grant from the Fonds canadien de revitalisation des communautés to be received under the Programme de développement économique du Québec/Fonds canadien de revitalisation des communautés ($750,000);

CONSIDERING THAT according to the presentation "Centre communautaire St-Gérard – Mise à jour financière" which was made by the Infrastructure and Projects Department and shared at the 2024 budget study week, the estimate for the completion of the community centre construction project is now $6,500,000, including professional fees, thus denoting a shortfall of $2,849,865;

CONSIDERING THAT the deadline to obtain the grant from the Fonds canadien de revitalisation des communautés is March 31, 2024, and that the grant amount has not been received to date; pending confirmation, it has been removed from the financing, leaving a shortfall of $3,599,865;

CONSIDERING THAT during the 2024 budget study week, this situation was presented and it was agreed that a resolution would be made to approve the use of the contingency fund when the Infrastructure and Projects Department reached the submission stage for the work, in order to have the final amount necessary for the completion of the project:

IT IS PROPOSED BY COUNCILLOR MARIO AUBÉ, SECONDED BY COUNCILLOR JEAN LESSARD, AND RESOLVED THAT following the recommendation of the executive committee number CE-2024-179 of March 26, 2024, this council finances from the contingency fund reserve the additional sum of $3,599,865 necessary for the reconstruction of the Centre communautaire Saint-Gérard. Should a grant of $750,000 be confirmed, it will be returned to the contingency fund reserve. To this effect, the treasurer is authorized to make the accounting entries required to give effect to this resolution. A treasurer's certificate was issued on March 25, 2024. Adopted

budgetinfrastructure adopted CM-2022-341CE-2024-179 St-Gérard Community Centrecontingency fundconstruction costsgrant $3,599,865
All items
CM-2024-250 #
Adoption of the Agenda
This is a routine procedural item where the City Council formally approves the agenda for the special meeting.
Read full translation

IT IS PROPOSED BY MAYOR DANIEL CHAMPAGNE, SECONDED BY COUNCILLOR STEVEN BOIVIN, AND RESOLVED THAT this council adopts the agenda as submitted. Adopted

CM-2024-252 #
Adjournment of the Meeting
This is a routine procedural item to formally close the special council meeting.
Read full translation

IT IS PROPOSED BY MAYOR DANIEL CHAMPAGNE, SECONDED BY COUNCILLOR STEVEN BOIVIN, AND RESOLVED THAT this council agrees to adjourn the meeting at 1:03 p.m. Adopted

STEVEN BOIVIN, Councillor and Chair Me VÉRONIQUE DENIS, City Clerk