Authorize a cost adjustment, with no budgetary impact - Bid 2020 SP 369 - Professional consulting engineering services - Environmental rehabilitation and soil decontamination - Fonderie site
This item authorizes a cost adjustment for environmental cleanup services at the former Fonderie site. The adjustment is budget-neutral for the city.
environmentinfrastructure
Authorize a cost adjustment, with no budgetary impact - Tender 2020 SP 369 - Professional consulting engineering services - Environmental rehabilitation and soil decontamination - Fonderie site
The city is approving an additional $251,041.86 for professional engineering services provided by WSP Canada inc. for the environmental cleanup of the Fonderie site. This covers extra work including environmental monitoring, chemical analysis, and risk assessment related to contaminated materials found at 211, rue Montcalm. The adjustment has no net budgetary impact.
environmentinfrastructure
2023-2024 Annual Activity Report under the Financial Assistance Agreement for the Decontamination and Upgrading of the Fonderie Site
The City is approving the 2023-2024 annual report for the decontamination and upgrading of the Fonderie site. Additionally, the City is requesting an extra $4 million in financial aid from the provincial government to continue and complete the decontamination project, citing increased costs and challenges.
environmentbudget
2023-2024 Annual Activity Report regarding the financial assistance agreement for the decontamination and upgrading of the Fonderie site
The city is reviewing the annual report on the decontamination and site improvement project at the former Fonderie site, as required by the financial assistance agreement.
environment
2023-2024 annual activity report according to the financial assistance agreement for the decontamination and upgrading of the Fonderie site
Council approved the 2023-2024 annual activity report for the Fonderie site decontamination project. Additionally, the city will request an additional $4 million in financial assistance from the provincial government to continue and complete the decontamination work.
environmentbudget
Authorize a tender cost adjustment, without budgetary impact - Loiselle inc. - 2021 SP 019 Environmental rehabilitation and soil decontamination - Fonderie site
The city has authorized a $971,589.82 cost adjustment for the environmental rehabilitation and soil decontamination project at the Fonderie site. This adjustment covers additional work recommended by engineering firm WSP Canada inc. and has no net budgetary impact.
environmentinfrastructure