218, boulevard Maisonneuve

8 agenda items mention this address

Conditional use - Construction of a mixed-use building with a maximum of 313 housing units - 218, boulevard Maisonneuve
This item concerns a request for a conditional use permit to allow the construction of a large mixed-use building containing up to 313 residential units at 218, boulevard Maisonneuve. This project is significant due to its scale and impact on housing density in the Hull-Wright district.
zoninghousing
Adoption of the Agenda
Council adopts the meeting agenda, including the withdrawal of several items related to 38, rue Court and other projects, and the addition of various items including new zoning requests, borrowing bylaws, and administrative appointments.
governance
Conditional Use - Construction of a Mixed-Use Building Including a Maximum of 313 Housing Units - 218, boulevard Maisonneuve - Hull-Wright Electoral District - Steve Moran
Council approved an increase in the number of housing units from 298 to 313 for the mixed-use building at 218, boulevard Maisonneuve. This change does not affect the building's footprint or volume and requires no additional parking.
zoninghousing
Derogation from Bylaw 44-2003 concerning noise on the territory of the City of Gatineau to authorize the company Développement Endokto inc. to carry out work outside permitted hours on boulevard Maisonneuve
The committee authorized Développement Endokto inc. to perform utility work outside of standard hours on boulevard Maisonneuve for approximately three weeks between July 3 and August 20, 2025, to minimize traffic disruption. The company must implement noise mitigation measures and inform nearby residents.
other
Agreement and request for municipal services for the Station 3 project at 218, boulevard Maisonneuve
The city is entering into an agreement with Développements Endokto inc. to install municipal services for the Station 3 project at 218, boulevard Maisonneuve. The developer will cover the costs of the infrastructure, and the city will contribute up to $16,000 for sidewalk widening work on rue Saint-Étienne.
infrastructurebudget
CES – Agreement and request - Servicing - Municipal services - Station 3 project at 218, boulevard Maisonneuve
This item concerns an agreement and request regarding the provision of municipal services for the 'Station 3' project located at 218, boulevard Maisonneuve.
infrastructure
Agreement and Request - Servicing - Municipal Services - Station 3 Project Located at 218, Boulevard Maisonneuve - Hull-Wright Electoral District - Steve Moran
The City has approved an agreement with Développements Endokto inc. to install municipal services for the 'Station 3' project on Boulevard Maisonneuve. The developer will cover all construction and supervision costs. The City will contribute up to $16,000 plus taxes for sidewalk widening on Rue Saint-Étienne.
infrastructurebudget
Information item – Application of the exception to the non-requirement of simultaneity for the issuance of the demolition authorization certificate and the building permit in the presence of contaminated land – 218, boulevard Maisonneuve (fire station block – Station 3) – Hull-Wright electoral district (7) – Steve Moran
This is an information item regarding the site at 218, boulevard Maisonneuve (Fire Station 3). It explains the application of a regulatory exception that allows for the demolition of a structure on contaminated land without requiring the immediate issuance of a building permit, which is typically a requirement for demolition permits.
otherenvironment