115, rue Principale
9 agenda items mention this address
Authorize a cost adjustment for work, with no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115 Rue Principale, Aylmer Sector - Project 19-2037 - Aylmer Electoral District - Vincent Roy
This item seeks approval for a cost adjustment regarding construction work at the Lucy-Faris Library. The adjustment is budget-neutral, meaning it does not require additional city funding.
budgetculture
Cost Adjustment - Lucy-Faris Library
This item authorizes a cost adjustment for work at the Lucy-Faris Library (115, rue Principale). The adjustment has no net impact on the city's budget.
culturebudget
Authorize a Cost Adjustment for Work, Without Budgetary Impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, Rue Principale
The committee approved a cost adjustment of $936,494.56 for the construction of the new Lucy-Faris Library. This adjustment covers various change orders and does not impact the overall budget.
cultureinfrastructure
Authorize a cost adjustment for work, with no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, rue Principale, Aylmer sector - Project 19-2037
This item authorizes a cost adjustment for construction work at the Lucy-Faris Library. The adjustment is budget-neutral, meaning it does not require additional funding from the city.
infrastructurebudgetculture
Authorize a cost adjustment for work, no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, rue Principale, Aylmer sector
The city is approving additional costs for the construction of the Lucy-Faris Library due to change orders. These extra costs, totaling $296,336.22 (including taxes), are being covered without requiring new budget allocations. The total adjusted contract value for the project is now $43,504,949.20.
infrastructurebudget
Authorize a cost adjustment for work, with no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, rue Principale, Aylmer sector - Project 19-2037
This item authorizes a cost adjustment for construction work at the Lucy-Faris Library. The adjustment is budget-neutral, meaning it does not require additional city funding.
infrastructurebudget
Authorize a cost adjustment for work, no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, Rue Principale
The committee approved additional costs of $395,988.34 for the construction of the Lucy-Faris Library. These costs, related to various change orders, do not require additional budget as they are covered within existing project allocations. The total adjusted contract value is now $43,208,612.98.
infrastructurebudget
Authorize a cost adjustment for work, with no budgetary impact - Tender 2022 SP 339 - Lucy-Faris Library - 115, rue Principale, Aylmer sector - Project 19-2037 - Aylmer electoral district - Steven Boivin
This item authorizes a budget-neutral cost adjustment for construction or renovation work at the Lucy-Faris Library. The change does not affect the overall project budget.
culturebudget
Authorization of a Cost Adjustment for Construction Work, No Budgetary Impact - Submission 2022 SP 339 - Lucy-Faris Library - 115, Rue Principale, Aylmer Sector
The City is approving an additional $531,284.80 for construction costs at the Lucy-Faris Library project in Aylmer. This covers change orders and additional work, bringing the total contract value to $42,812,624.64, with no impact on the city budget.
infrastructurebudget