CE-2024-808 #
Authorize a cost adjustment for professional engineering fees, budget-neutral - Stantec Experts-conseils ltée., municipal service repairs on Rue Charles-Desnoyers and in the Rue Ducerre sector
The city is approving an additional $42,419.92 in professional fees for Stantec Experts-conseils ltée. for ongoing municipal infrastructure work on Rue Charles-Desnoyers and Rue Ducerre. This adjustment covers additional site and office supervision costs. The total revised contract value is $362,403.82, and the city confirms this adjustment has no additional impact on the municipal budget.
Read full translation

CONSIDERING THAT this committee, by its resolution number CE-2019-129 of March 13, 2019, awarded a mandate to the consulting engineering firm Stantec Experts-conseils ltée. for the design, preparation of plans and specifications, and site supervision for municipal service repair work on Rue Charles-Desnoyers and in the Rue Ducerre sector, for an approximate total amount of $236,768.76 including taxes;

CONSIDERING THAT this committee, by its resolution number CE-2022-316 of April 27, 2022, authorized a cost adjustment for professional consulting engineering fees in the amount of $55,045.93 including taxes, to the firm Stantec Experts-conseils ltée., for additional design and site supervision as part of the municipal service repair work on Rue Charles-Desnoyers and in the Rue Ducerre sector, bringing the total cumulative amount of the mandate to $291,814.69 including taxes;

CONSIDERING THAT delegation of power number 191342 has already been approved for an amount of $28,169.21 including taxes;

CONSIDERING THAT the firm Stantec Experts-conseils ltée. has filed an additional request for professional fees with the City in the amount of $42,419.92 including taxes, for additional site and office supervision as well as an adjustment of supervision fees, bringing the cumulative total of adjustments to be approved to $70,589.13 including taxes;

CONSIDERING THAT under Règlement 816-2017 concerning the delegation of power from the executive committee to certain officials, including the power to authorize expenditures and enter into contracts on behalf of the City of Gatineau, a resolution of the executive committee is required since the adjustment amount exceeds the limit provided for in the bylaw;

CONSIDERING THAT after verification, the Infrastructure and Projects Department recommends this cost adjustment for the additional professional fees incurred:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee:

• ratifies delegation of power number 191342, for an amount of $28,169.21 including taxes; • authorizes the cost adjustment for additional professional fees incurred in the amount of $42,419.92 including taxes, to the firm Stantec Experts-conseils ltée., without budgetary impact, as part of the municipal service repair project on Rue Charles-Desnoyers and in the Rue Ducerre sector, thus bringing the cumulative total of adjustments to be approved to an amount of $70,589.13 including taxes.

The total revised cost of the mandate, following this adjustment, represents an amount of $362,403.82 including taxes. A treasurer's certificate was issued on November 22, 2024.

infrastructurebudget adopted Lac-BeauchampTouraine Rue Charles-DesnoyersRue Ducerre Règlement 816-2017 StantecCharles-DesnoyersDucerreinfrastructureengineering $70,589.13
CE-2024-811 #
Periodic review of property tax exemption recognition by the Commission municipale du Québec - L'Amicale des personnes handicapées physiques de l'Outaouais - 405 Rue Notre-Dame
The city is supporting the renewal of a property tax exemption for the organization 'L'Amicale des personnes handicapées physiques de l'Outaouais' for their building at 405 Rue Notre-Dame. This is a periodic review required by provincial law every nine years. The city will defer to the decision of the Commission municipale du Québec and will not attend any potential hearings on the matter.
Read full translation

CONSIDERING THAT the organization L'Amicale des personnes handicapées physiques de l'Outaouais obtained, on February 17, 2015, recognition for property tax exemption purposes for the building located at 405 Rue Notre-Dame, with the exception of the apartment on the 2nd floor of the building;

CONSIDERING THAT the Loi sur la fiscalité municipale provides for the periodic review of the recognition every nine years;

CONSIDERING THAT the organization L'Amicale des personnes handicapées physiques de l'Outaouais has requested the renewal of the property tax exemption for the building located at 405 Rue Notre-Dame;

CONSIDERING THAT the Commission municipale du Québec may confirm the recognition of the property tax exemption after consultation with the City:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee agrees to defer to the decision of the Commission municipale du Québec to confirm the recognition of the property tax exemption granted to the organization L'Amicale des personnes handicapées physiques de l'Outaouais for the building located at 405 Rue Notre-Dame;

Furthermore, this committee wishes to inform the Commission municipale du Québec that should a hearing be held to allow for a decision in this file, the City will not be present.

CE-2024-812 #
Acquisition by the City - Section 72 of the Municipal Powers Act - Rue Coulombe, Rue Cadieux, and part of Rue Duquette Ouest
The city is formally acquiring ownership of Rue Coulombe, Rue Cadieux, and a portion of Rue Duquette Ouest. These streets have been open to public traffic for years, but the title was never officially transferred from the original company. This process follows the Municipal Powers Act to ensure the city holds legal title to these public roads.
Read full translation

CONSIDERING THAT Rue Coulombe, Rue Cadieux, and Rue Duquette Ouest were built and developed several years ago;

CONSIDERING THAT according to the property index of the Land Registry Office of the circonscription foncière de Hull, it appears that the transfer of titles for these streets has not been carried out and that the lots still belong to a company;

CONSIDERING THAT section 72 of the Loi sur les compétences municipales allows a local municipality to become the owner of any road open to public traffic for at least 10 years, when the formalities prescribed by law have been completed, which are:

  1. The municipality adopts a resolution identifying the road concerned, either by its cadastral designation when its footprint corresponds to that of one or more whole lots of the current cadastre, or, otherwise, by a technical description prepared by a land surveyor;
  2. Where applicable, a copy of the technical description, certified by a land surveyor, is filed at the Municipality's Office;
  3. The municipality publishes twice, in a newspaper distributed on its territory, a notice containing:
    • the full text of this article;
    • a summary description of the road concerned;
    • a declaration stating that the formalities provided for in paragraphs 1 and 2 have been completed;
  4. No property tax has been levied by the municipality over the last 10 years;

CONSIDERING THAT despite the procedures prescribed by section 72 of the Loi sur les compétences municipales, the City adopted Règlement 851-2023 on the procedures for publishing notices under section 345.1 of the Loi sur les cités et villes (RLRQ c C-19), taking precedence over the procedures prescribed by that same Act or by any other laws, allowing the publication of the two notices on the City of Gatineau's website;

CONSIDERING THAT the City of Gatineau deems it in the public interest to avail itself of this procedure to obtain a valid property title for these streets:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee decrees that the City of Gatineau intends to avail itself of the procedure enacted in section 72 of the Loi sur les compétences municipales regarding the obtaining of the property title for lots 1 770 132, 1 770 138, and 1 770 447 of the cadastre du Québec, circonscription foncière de Hull, as being Rue Coulombe, Rue Cadieux, and part of Rue Duquette Ouest and, to this effect, recognizes the cadastral designation identifying the roads concerned.

It is further resolved that this committee mandates the City Clerk's Office to follow up on this and authorizes the City Clerk or, in her absence, the Deputy City Clerk or the Assistant City Clerk to sign the declarations of ownership to be published at the Land Registry Office.

governanceinfrastructure adopted Lac-Beauchamp Rue CoulombeRue CadieuxRue Duquette Ouest Règlement 851-2023 acquisitionCoulombeCadieuxDuquetteMunicipal Powers Act
CE-2024-813 #
Agreement to be signed with Chemins de fer Québec-Gatineau inc. to establish responsibilities regarding the widening of the crossing surface on Avenue Lépine
The city is entering into an agreement with the railway company 'Chemins de fer Québec-Gatineau inc.' to widen a railway crossing on Avenue Lépine. This work is necessary to accommodate a new multi-use path. The city will pay $21,500.33 for the crossing improvements.
Read full translation

CONSIDERING THAT the City of Gatineau has carried out development work for a multi-use path on the south side of Avenue Lépine, between Avenue de Buckingham and Chemin Findlay;

CONSIDERING THAT Avenue Lépine, between Avenue de Buckingham and Chemin Findlay, crosses a railway track at mile point 2.36 of the Buckingham branch, belonging to the company Chemins de fer Québec-Gatineau inc. and that the level crossing requires widening work on the crossing surface to accommodate the development of the new multi-use path:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee:

• authorizes the signing of agreement no. 129_002-36 XRAG regarding the widening of the crossing surface, at mile point 2.36 of the Buckingham branch, belonging to the company Chemins de fer Québec-Gatineau inc.; • authorizes the expenditure of $21,500.33 including taxes, to the company Chemins de fer Québec-Gatineau inc., to cover the cost of the widening work for the Avenue Lépine level crossing to accommodate the development of a multi-use path on the south side of the road.

The funds for this purpose will be taken from sub-project 21517.01 - SIS RAU-FDI-19-3070 Piste avenue Lépine – Construction and improvement of the cycling network – règlement 852-2020.

A treasurer's certificate was issued on November 22, 2024.

infrastructuretransit adopted Buckingham Avenue LépineAvenue de BuckinghamChemin Findlay Règlement 852-2020 railwayAvenue LépineChemins de fer Québec-Gatineaumulti-use path $21,500.33
CE-2024-814 #
Authorize a bid cost adjustment, budget-neutral - Restoration of the building at 205 Rue Montcalm
The city is approving an additional $170,137.80 for the restoration of the building at 205 Rue Montcalm, bringing the total contract adjustment to $373,357.35. This covers necessary additional costs for the project managed by Gestion DMJ. The city confirms this adjustment has no impact on the municipal budget.
Read full translation

CONSIDERING THAT under resolution number CE-2022-560 of June 29, 2022, the City of Gatineau awarded a contract to the firm 6739741 Canada inc. (Gestion DMJ), for the restoration work of the building at 205 Rue Montcalm, for a total amount of $4,570,831.13 including taxes;

CONSIDERING THAT additional costs covered by change orders for an amount of $203,219.55 including taxes, were authorized under delegations of power numbers 190335, 191156, and 192922 and modification notices numbers 10084 and 10262;

CONSIDERING THAT the professionals on the file recommend a total amount of $170,137.80 including taxes, for the completion of all additional costs that have been necessary to date;

CONSIDERING THAT under Règlement 816-2017 concerning the delegation of power from the executive committee to certain officials, including the power to authorize expenditures and enter into contracts on behalf of the City of Gatineau, a resolution of the executive committee is required since the cumulative amount of additional fees exceeds the 10% limit provided for in the bylaw or is greater than $250,000 including taxes;

CONSIDERING THAT after analysis, the Infrastructure and Projects Department recommends the approval of these additional costs:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee:

• ratifies the delegations of power numbers 190335, 191156, and 192922 and the modification notices numbers 10084 and 10262 for a total amount of $203,219.55 including taxes; • authorizes the additional amount of $170,137.80 including taxes, to the contract of Gestion DMJ, thus bringing the bid cost adjustment to the amount of $373,357.35 including taxes, without budgetary impact.

The total cost of this adjusted contract represents an amount of $4,944,188.48 including taxes. The funds for this purpose will be taken from sub-projects 20505.01 and 21237.01.

A treasurer's certificate was issued on November 22, 2024.

infrastructurebudget adopted Hull-Wright 205, rue Montcalm Règlement 816-2017 restoration205 Rue MontcalmGestion DMJcontract adjustment $373,357.35
All items
CE-2024-807 #
Minutes of the Executive Committee meeting held on November 13, 2024
This is a routine procedural item to formally approve the minutes of the previous Executive Committee meeting.
Read full translation

CONSIDERING THAT a copy of the minutes of the regular meeting of the Executive Committee of the City of Gatineau held on November 13, 2024, was provided to the Executive Committee:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee adopts the minutes as submitted.

CE-2024-809 #
Parking signage modifications - Rue Robert-Wright and Rue Prentiss - Aylmer district
The city is implementing new 'no parking' zones on Rue Robert-Wright and Rue Prentiss in the Aylmer district to improve traffic flow and safety. These changes replace all previous parking regulations in the specified areas.
Read full translation

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee decrees modifications to the parking signage on Rue Robert-Wright and Rue Prentiss, file RS-24-260, as illustrated in plan number CRO-24-374 dated October 3, 2024, all in order to:

Implement a no-parking zone:

Street Side Location In effect
Robert-Wright East From Rue Prentiss, for a distance of 76 m northward At all times
Prentiss North From Rue Robert-Wright, for a distance of 17 m eastward At all times
Prentiss North From Rue Robert-Wright, for a distance of 17 m westward At all times

This resolution cancels or replaces any previous signage governing parking in the parking zone mentioned herein. The Public Works Department is authorized to proceed with the installation of the required regulatory signage, all according to the directives of the Mobility Department, in accordance with plan number CRO-24-374 which is an integral part of this document.

CE-2024-810 #
Parking signage modification - Boulevard de la Cité-des-Jeunes - Orée-du-Parc district
The city is removing a 'no stopping' zone on Boulevard de la Cité-des-Jeunes to adjust parking regulations in the area.
Read full translation

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee decrees a modification to the parking signage on Boulevard de la Cité-des-Jeunes, file RS-24-306, as illustrated in plan number CRO-24-466 dated October 28, 2024, all in order to:

Remove a no-stopping zone:

Street Side Location In effect
Cité-des-Jeunes East From a point located 38 m south of Rue Talbot, for a distance of 18 m southward At all times

The Public Works Department is authorized to proceed with the installation of the required regulatory signage, all according to the directives of the Mobility Department, in accordance with plan number CRO-24-466 which is an integral part of this document.

CE-2024-815 #
Administrative termination of employment - Employee number 106959
The city is terminating the employment of an individual who has been on medical leave since 2022, as medical reports confirm they are permanently unable to perform their duties.
Read full translation

CONSIDERING THAT employee number 106959 has been employed by the City of Gatineau since June 28, 2004;

CONSIDERING THAT employee number 106959 has been on work stoppage since July 18, 2022, and their medical prognosis confirms that employee number 106959 will no longer be able to provide constant and regular work performance at the City of Gatineau, on a permanent basis:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee accepts the termination of the employment relationship of employee number 106959.

CE-2024-816 #
Administrative termination of employment - Employee number 118556
The city is terminating the employment of a probationary employee who failed to meet the requirements of their position despite additional support and an extended probationary period.
Read full translation

CONSIDERING THAT employee number 118556 was hired on September 5, 2023;

CONSIDERING THAT since their hiring as a probationary employee, employee number 118556 has shown deficiencies in the execution of their tasks and does not meet all the normal requirements of their position;

CONSIDERING the extension of the employee's probationary period by the department, as well as the efforts made to offer them the necessary support to help them correct the identified deficiencies and meet expectations;

CONSIDERING the work performance deemed unsatisfactory at the end of the additional period granted to employee number 118556;

CONSIDERING THAT the representatives of the Human Resources Department and the department concerned authorize this recommendation:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee authorizes the administrative termination of employment of employee number 118556.

CE-2024-817 #
4-month suspension without pay - Employee number 116600
The city is imposing a four-month suspension without pay on an employee following an internal investigation into misconduct.
Read full translation

CONSIDERING the conclusions of the investigation conducted by the representatives of the City of Gatineau;

CONSIDERING the nature of the breaches committed by employee number 116600;

CONSIDERING all the facts analyzed, internal equity, as well as the current state of jurisprudence in this matter;

CONSIDERING THAT the representatives of the Human Resources Department and the department concerned authorize the conclusions following the investigation:

PROPOSED AND RESOLVED UNANIMOUSLY THAT this committee authorizes the imposition of a four-month suspension without pay on employee number 116600.